A Review of Application of Risk Management Techniques
in Costing and Evaluating Construction Work Projects in
Nigeria: A Mathematical Analysis Approach
Volume 5 - Issue 4
Sebastian O Uremadu1*, Florence O Ariwa2 and Charity E Duru Uremadu3
-
Author Information
Open or Close
- 1Department of Banking and Finance, MOUAU, Nigeria
- 2Department of Banking and Finance, Michael Okpara University of Agriculture, Nigeria
- 3Department of Educational Management, MOUAU, Nigeria
*Corresponding author:
Sebastian O Uremadu, Department of Banking and Finance, MOUAU, Nigeria
Received: November 19, 2018; Published:November 30, 2018
DOI: 10.32474/CIACR.2018.05.000216
Full Text
PDF
To view the Full Article Peer-reviewed Article PDF
Summary
There exist some inherent risk elements like physical risk, environmental risk, logistic risk, financial risk, legal risk, political risk,
etc. in the construction work environment in Nigeria. Before now those costing these projects use only contingency sum approach
and insurance cover without properly taking into consideration all these other critical factors of risk. The result is that most contract
projects that border on, construction works were either over-valued or under-valued with their consequent rising cost implications,
before execution contract agreement is signed. The present paper used secondary data compiled by a Consultant Quantity Surveyor
to carry out some evaluation tests and analysis through the use of an established model that combined material cost (M), labour
cost (L) and Plant cost (P) to arrive at a total “best” construction cost estimates (TCCE). That is, TCCE = M+ L + P. Major objectives
the paper tried to achieve, are: [1] possibility of using risk management techniques, namely; risk identification, risk analysis and
risk response, to ascertain cost variables that could combine to give an optimum cost estimate in order to avoid cost over-runs
in construction work project, [2] To ascertain their applicability in Nigerian, in addition to, use of cost effectiveness, cost-benefit
analysis and sensitivity analysis (simulation) methods in evaluating and determining the viability of government Projects/Programs
in Nigeria. Results from the study confirmed our convictions that it was possible to find total “best” construction cost estimates
through an established model that incorporated most key risk factors (variables) inherent in projects as well as use qualitative
evaluation techniques to access government project and programs. It is therefore recommended that investors and all stakeholders
to construction work project contracts always use a model that captures or incorporates key indicators of risk to arrive at total best
construction cost estimates so as to avoid cost over-runs in project execution and outright abandonment.
Abstract|
Introduction|
Methodology|
Decision|
Findings, Conclusion and Recommendations|
References|